February update Barney

on Tuesday, 17 February 2015. Posted in news

Since the arrival of the hull of our newest vessel Shoalbuster Barney, a lot has been done. The last 6 weeks the shipyard worked hard to ensure they would make the delivery date of 1st of May 2015. And all the hard work they put in is showing, especially in the engine room and the accommodation.

Both air compressors have been installed as well the sewage plant. In the aft peak the rudder installation is already in place and some of the floor plates are in place. Not only in the aft peak, but also in the engine room the foundation of the floor plates is being placed as well.

Meanwhile the accommodation has been fully decorated with isolation material and the floors have been placed. Because of this the view has been changed significantly. In the mess room most of the piping and drains have been placed. And in the tween deck the full ventilation installation has been placed. This week the carpenters will start on the paneling inside; once this is started the accommodation will start to take look like a ship.

Outside is still looking like before, only difference is that both tugger winches and anchor winches have been placed. But this is due to the fact that Barney is still lying in the water. Next week around 26 of February, the Barney will go inside the shed of Damen Gorinchem. Once she is inside the outside works can start such as painting and placing of the towing winch and hydraulic cranes.

Hereby some nice photo's of the Barney.

 GOPR8368

GOPR8369

GOPR8370

GOPR8371

GOPR8376

GOPR8377

GOPR8379

GOPR8381

GOPR8382 

GOPR8383

GOPR8387

GOPR8389

GOPR8390

GOPR8391

GOPR8392

GOPR8398

GOPR8399

GOPR8401

GOPR8403

Contact Us


Holding Hermansr BV
Aventurijn 202
3316LB Dordrecht
The Netherlands

T: +31 (0)78 6192507
E: info@hermansr.com
I: www.hermansr.com

Sitemap | Disclaimer | Planning